| Jim Haberl Hut Construction Schedule - Spring 2006 | ||||||||||||||||
| ALL VOLUNTEERSÉ | ||||||||||||||||
| Read carefully: | Letter: | http://www.jimhaberlfund.org/files/Haberl_Hut_Volunteer_info.pdf | ||||||||||||||
| Gear List: | http://www.jimhaberlfund.org/files/JHHut_EquipList.pdf | |||||||||||||||
| Sign and return: | Waiver: | http://www.jimhaberlfund.org/files/ACC_Waiver.pdf | ||||||||||||||
| Contact: Alastair Foreman - 604-904-0509 | AlastairForeman@shaw.ca | |||||||||||||||
| TRIP | TASKS | PEOPLE | MATERIALS | |||||||||||||
| #1 | Sat May 6 to Wed eve May 10 (5 days) | generator | ||||||||||||||
| Check hut condition - repair winter damage if any | elect materials | |||||||||||||||
| Rough-in electrical for lighting & heater timer | Peter Taylor | foam insulation | ||||||||||||||
| CEILING INSULATION | Doug Swanston | white insulation ? | ||||||||||||||
| Foam insulate door frames | Olivier Lardin | utility knives | ||||||||||||||
| Temporarilly install heater | some type of stop | |||||||||||||||
| Shovel out door to crawlspace | propane heater & tank | |||||||||||||||
| Level snow for heli drop of materials near hut | scaffold | |||||||||||||||
| Rough-in vent for stove | satphone & first aid kit | |||||||||||||||
| Check blocking & backframing | vent materials | |||||||||||||||
| Frame vestibule wall | heat-resistant insulation | |||||||||||||||
| Install bolts to support ext signage & shutters | Tuck tape | |||||||||||||||
| POLY VAPOUR BARRIER | staples | |||||||||||||||
| AIRLIFT OF PLYWOOD | ||||||||||||||||
| LUMBER & TOOLS UP / | ||||||||||||||||
| GARBAGE OUT | ||||||||||||||||
| #2 | Wed eve May 10 to Fri eve May 19 (9 days) | compressor | ||||||||||||||
| FINISH CARPENTRY WEEK | Chris Kiely | saws | ||||||||||||||
| Install ceiling T&G | Britt Beach | pine tongue & groove | ||||||||||||||
| Install 2 interior wood doors | (framing needs adjusting) | Bob Woodhouse | 2 doors | |||||||||||||
| Install interior wall sheathing | interior plywood | |||||||||||||||
| Install interior window & door trim | casing nails | |||||||||||||||
| If time, sand & finish glulam | urethane finish | |||||||||||||||
| If time, install exterior window & door trims | (incl outhouse) | pre-stained casings & sills | ||||||||||||||
| If time, install missing fascia | battens | |||||||||||||||
| If time, install battens at panel joints, corners | lumber for fascia | |||||||||||||||
| AIRLIFT OF TOOLS OUT / | ||||||||||||||||
| MILLWORK IN | ||||||||||||||||
| #3 | Fri eve May 19 to Mon eve May 22 (3 days) | |||||||||||||||
| MILLWORK | bunks & ladders | John Lawless | millwork package | |||||||||||||
| kitchen cabinets | Edward Ingham | lumber & plywood | ||||||||||||||
| kitchen countertop | Milton McCrystall | handles | ||||||||||||||
| cubbies | ss countertop | |||||||||||||||
| backboards & hooks | sink | |||||||||||||||
| shelves | bench carpet | |||||||||||||||
| bench | hooks | |||||||||||||||
| AIRLIFT OF TOOLS OUT / | ||||||||||||||||
| TANK & FITTINGS IN | ||||||||||||||||
| #4 | Mon eve May 22 to Fri eve May 26 (4 days) | |||||||||||||||
| WATER SYSTEMS | Manrico Scremin | piping & strainer | ||||||||||||||
| Plumb sink - grey water system | Plumber/Gas Fitter | plastic urinal & piping | ||||||||||||||
| Plumb urinal | Volunteer needed | lumber ? | ||||||||||||||
| Construct platform for tank | gutter | |||||||||||||||
| Install gutter & rainwater leader | rainwater leader | |||||||||||||||
| Install tank & fittings | tank & fittings | |||||||||||||||
| Install overflow drainpipe | foot pump | |||||||||||||||
| Install water foot pump | gas piping | |||||||||||||||
| PROPANE | cooktops | 2 cooktops | ||||||||||||||
| AIRLIFT OF ? OUT / | ||||||||||||||||
| FLOOR PLY & LUMBER IN | ||||||||||||||||
| #5 | Fri eve May 26 to Mon eve May 29 (3 days) | |||||||||||||||
| FINAL FLOOR | Sink nails | Lawrence Macintosh | angle grinder | |||||||||||||
| Fill gaps & sand | Volunteer needed | 20 sheets floor plywood | ||||||||||||||
| Screw down plywood | Volunteer needed | baseboards & battens | ||||||||||||||
| Stain floor | filler | |||||||||||||||
| Install baseboards | screws | |||||||||||||||
| Install battens | stain, brushes | |||||||||||||||
| AIRLIFT OF ? OUT / | ||||||||||||||||
| FURNITURE & FITTINGS IN | ||||||||||||||||
| #6 | Mon eve May 29 to Fri eve June 2 (4 days) | tables & chairs | ||||||||||||||
| FURNISHINGS | Liz Scremin | mattresses & kitchen gear | ||||||||||||||
| STAINING & PAINTING | fascia | Melinda Straight | stain | |||||||||||||
| window/door trims | tsp or bleach | |||||||||||||||
| Interior painting | interior walls of outhouse | Bridget Milsom ? | Polyurethane, brushes, etc | |||||||||||||
| Install tp holder/shelf in outhouse | Milton McCrystal? | paint for ply walls | ||||||||||||||
| Paint metal doors & frames | (remove glazing tape) | tp holder / shelf | ||||||||||||||
| Install window vents & lock-downs | paint for metal doors | |||||||||||||||
| Install glass in metal doors | window vents & lock-dns | |||||||||||||||
| Install signage | glazing tape | |||||||||||||||
| signs | ||||||||||||||||
| AIRLIFT OF ? OUT / | ||||||||||||||||
| DRILL & LUMBER IN | ||||||||||||||||
| #7 | Fri eve Jun 2 to Wed eve Jun 7 (5 days) | |||||||||||||||
| DECK & GUARDRAIL | Peter Taylor | rock drill | ||||||||||||||
| Footings for expanded deck | Chris Kiely? | lumber | ||||||||||||||
| Deck structure | decking | |||||||||||||||
| Decking | prepared lumber | |||||||||||||||
| Guardrail | wire rope system | |||||||||||||||
| Complete framing clips at crawlspace | framing clips? | |||||||||||||||
| Replace ply at crawlspace ceiling | plywood? | |||||||||||||||
| Install chicken wire at crawlspace ceiling? | ||||||||||||||||